What Is a Change Order in Remodeling? (Full Guide)

A change order is a written amendment to your remodeling contract that documents any change to scope, cost, or schedule. Both parties must sign before work on that change begins. Verbal agreements have no legal weight.

What a change order actually is

When you sign a remodeling contract, you are agreeing to a defined scope of work at a defined price. A change order is the mechanism for modifying that agreement after work has started. It is not a request, a conversation, or an email. It is a signed document that becomes part of the contract.

Change orders exist to protect both parties. The homeowner gets a written record of exactly what changed and what it costs. The contractor gets written authorization before spending money on unapproved work. Without that document, disputes over cost and scope are nearly impossible to resolve cleanly.

The two types of change orders, and why the distinction matters

Owner-initiated changes

You decide you want a different tile, want to expand the shower, or want to relocate a wall that was not in the original plan. These changes are your decision, and you have negotiating room. You can compare the contractor’s cost to what materials actually run, ask for competing quotes on the labor portion, and push back on markup if it seems high.

Condition-driven changes

The contractor opens a wall and finds plumbing that does not meet current code, discovers termite damage in the subfloor, or hits unexpected concrete under your slab. In the Valley, older homes in areas like Central Phoenix or parts of Mesa sometimes carry decades-old plumbing or electrical that must be brought up to code before the finish work can proceed. These changes are not optional. You have less negotiating power because the work must be done, but you are still entitled to a written change order with a line-item breakdown before the contractor proceeds.

Key insight
Your negotiating position is much stronger on owner-initiated changes than on condition-driven ones. For conditions discovered in the field, the work is usually required by code or structural necessity, so the conversation shifts from whether to do it to making sure the price is fair and documented.

What every change order document must include

A change order that leaves out key fields is an invitation to a dispute. Every change order should contain all of the following:

FieldWhat it should say
Project name and addressIdentifies which job the CO applies to
Original contract referenceContract number or date the CO amends
Change order numberSequential, so both parties can track the history
Description of scope changePlain-language explanation of exactly what is added, removed, or modified
Line-item cost breakdownMaterials and labor listed separately, not as a single lump sum
Contractor markupThe overhead and profit percentage applied, stated explicitly
Timeline impactHow many calendar days this change adds to the schedule, if any
Revised contract totalThe new running total after this change order is added
Signatures and datesBoth homeowner and contractor, dated on the same day if possible

Each party should retain a signed copy. If your contractor uses a digital signature platform, make sure you download and save the executed PDF.

What contractor markup on a change order looks like, and what is fair

This is the number most homeowners never ask about and most competing pages never explain. When a contractor prices a change order, the math typically works like this:

Materials cost plus labor cost equals a subtotal. The contractor then applies an overhead and profit margin on top of that subtotal. In the remodeling industry, 10 to 20 percent is the standard range for that markup. Some contractors apply it only to materials; others apply it to both materials and labor. Neither approach is inherently wrong, but the contractor should disclose which method they use.

If you receive a change order with a single lump-sum number and no breakdown, ask for the line-item version before you sign. A reputable contractor will provide it without pushback. If the markup comes in above 20 percent and the contractor cannot justify it, that is worth a direct conversation.

10-20%
standard contractor markup on change orders
10-15%
recommended budget contingency to cover change orders
$0
legally enforceable value of a verbal change agreement

The step-by-step change order process

1
Change is identified. Either you request a modification or the contractor discovers a condition in the field that requires a scope change.
2
Work on the change stops. No materials are ordered and no labor is performed on the new scope until a signed change order exists. This is a firm rule, not a guideline.
3
Contractor prepares the written change order. The document includes all fields listed in the table above, with line-item pricing and a stated markup percentage.
4
Homeowner reviews and asks questions. This is the time to request a line-item breakdown if you did not receive one, to verify the timeline impact is realistic, and to push back on any markup that seems outside the standard range.
5
Both parties sign and date the document. Do not let days pass on this. Delays stall the project and can ripple into other trades already scheduled on-site.
6
Each party keeps a copy. File it with your original contract. If a payment dispute or lien issue ever arises, your complete change order log is essential documentation.
7
Work on the change proceeds. The contractor can now order materials, schedule trades, and perform the new scope without ambiguity about authorization or payment.

Pro Tip: Number every change order sequentially starting at CO-001. When you have three or four changes on a kitchen or addition project, a numbered log lets you track the running contract total without recalculating from scratch each time.

When a change order triggers a permit amendment

This is the gap every competing page leaves out entirely. If a change order modifies work that is covered by an existing permit, it may require an amended permit from the city or municipality before the work can proceed. This matters a lot in the Valley because permitting is handled city by city, and the requirements in Scottsdale differ from those in Chandler or Tempe.

Common scenarios where a change order triggers a permit amendment include relocating a load-bearing wall that was not in the original permitted plans, adding a window or exterior door not shown on the approved drawings, moving a gas line or electrical subpanel to a new location, or increasing the square footage of an addition.

The contractor is typically responsible for filing the permit amendment, but the cost of that filing and any resulting inspection delays should be reflected in the change order itself, not absorbed silently into overhead. Ask explicitly: does this change require an amended permit, and if so, what is the timeline impact?

Change orders by project type, and what tends to trigger them

Kitchen remodels

For a full kitchen remodel in Phoenix running 50,000 to 100,000 dollars, the most common condition-driven change orders involve outdated electrical panels that cannot support a modern appliance package, plumbing that does not align with a new island layout, or HVAC ducts that run directly through a wall you wanted to open. Valley homes built in the 1970s and 1980s frequently have aluminum wiring or single-circuit kitchens that must be upgraded before the city will pass inspection. If you are planning kitchen remodeling in Phoenix or kitchen remodeling in Scottsdale, build at least 10 percent contingency into your budget for these scenarios.

Bathroom remodels

Bathroom remodels running 15,000 to 50,000 dollars are where hard water damage creates unpleasant surprises. When tile comes off a shower wall, contractors sometimes find that years of hard water infiltration have compromised the cement board or the substrate behind the tile. That is a condition-driven change order that is difficult to anticipate without opening the wall. For bathroom remodeling in Phoenix, factor this in if the existing shower is more than 15 years old.

Additions and ADUs

Additions and ADUs, which run 300 to 500 dollars or more per square foot for a room addition or primary suite, are the most likely project type to generate multiple condition-driven change orders. Tying a new addition into an existing slab, matching rooflines, and connecting to existing plumbing and electrical all carry discovery risk. Permit amendments on additions are common and should be expected in the project budget.

Pro Tip: For any project involving an addition or ADU, ask your contractor before signing the original contract what specific conditions, if discovered, would trigger a change order. Getting a list of likely scenarios in writing reduces surprises and sets realistic expectations from the start.

Red flags in how contractors handle change orders

Beyond the universal warning about verbal agreements, watch for these specific behaviors:

Work started before you sign. If a contractor begins the new scope before you have a signed change order, they are either disorganized or counting on the sunk-cost pressure to get you to approve the price after the fact. Neither is acceptable.

Retroactive change orders. A change order presented after the work is already complete gives you no leverage. You should never be signing a change order for work that has already been done.

Bundling unrelated changes. When a contractor groups three or four unrelated items into a single change order, it makes it very difficult to evaluate whether each line is fairly priced. Ask for separate change orders by scope if the items are unrelated.

No timeline disclosure. Every change order should state whether it affects the project schedule and by how many days. A change order that is silent on timeline is incomplete.

Markup that is not stated explicitly. If the change order shows a lump sum with no breakdown, that is a document you should not sign until the breakdown is provided.

Change orders and lien rights

In Arizona, a licensed contractor can file a mechanics lien against your property for unpaid work, and change orders are part of that equation. If you authorized work through a signed change order and then dispute the invoice, the contractor has documentation supporting the amount owed. Conversely, if a contractor performs work without a signed change order and then tries to collect, their position is weaker. This is another reason the written, signed change order protects both parties, not just one.

Arizona licenses contractors through the Registrar of Contractors. Bayside Home Builders is licensed, bonded, and insured under ROC 353387, verifiable at azroc.gov. Working with a licensed contractor means that disputes have a formal avenue for resolution beyond civil court.

A reference template for what a change order should include

You will not always receive a change order that is formatted this way, but comparing what you receive against this list tells you immediately what is missing.

FieldExample entry
Project address4821 E. Camelback Rd., Phoenix, AZ 85018
Original contract dateMarch 3, 2026
Change order numberCO-002
Date issuedApril 14, 2026
Description of changeRelocate kitchen sink 36 inches to align with new island position; reroute supply and drain lines accordingly
Materials cost$820
Labor cost$1,100
Subtotal$1,920
Overhead and profit (15%)$288
Change order total$2,208
Timeline impact2 additional calendar days
Revised contract total$67,208
Permit amendment requiredYes, filed by contractor; estimated 5 to 7 business days for city approval
Homeowner signature and dateSigned, April 15, 2026
Contractor signature and dateSigned, April 15, 2026

Pro Tip: Keep a running spreadsheet with one row per change order: the CO number, the amount, and the revised contract total. By the end of a kitchen or addition project, it is easy to lose track of cumulative changes without that log, and you want to know the running total before the final draw is due.

How to prevent excessive change orders

The most effective prevention is thorough pre-construction design. The more decisions finalized on paper before anyone picks up a tool, the fewer mid-project surprises. This means selecting every material, appliance, and fixture before the contract is signed, not after demolition begins.

For Valley homes specifically, a pre-construction walkthrough that includes opening one or two inspection points in walls or ceilings can surface hidden conditions before they become emergency change orders. This adds a small cost upfront and can eliminate several thousand dollars in surprises later.

Build a 10 to 15 percent contingency into your budget before the project starts. If you budget 80,000 dollars for a kitchen remodel, treat 8,000 to 12,000 dollars of that as your change order reserve, not as free money. Projects that come in under budget return that money to you. Projects that hit unexpected conditions spend it on documented, signed change orders rather than on disputes.

Frequently asked questions

What should every change order document include?
A proper change order includes the project name and address, the original contract reference, a description of the new or modified scope, a line-item cost breakdown with materials and labor listed separately, the contractor markup percentage, any timeline impact, the new contract total after the change, and dated signatures from both the homeowner and contractor.

What is the difference between a change order and an addendum?
An addendum is issued before the original contract is signed and adds terms before work begins. A change order modifies an already-executed contract after the project is underway. Both require signatures, but only change orders affect an active scope of work.

What percentage of markup is normal on a remodeling change order?
Most contractors apply 10 to 20 percent overhead and profit on top of the actual materials and labor cost on a change order. That range is standard. If the markup is higher, ask for a written line-item breakdown showing labor hours, material costs, and the markup percentage separately.

How do I write out a change order?
Start with the project name, address, and original contract date. Describe the specific scope change in plain language. List materials and labor costs as separate line items, then add the markup percentage and the total. State whether the project timeline changes and by how many days. Both parties sign and date it, and each keeps a copy.

What happens if I delay approving a change order?
Work on the affected portion of the project stops until you sign. Delays can push back your overall completion date and sometimes hold up other trades already scheduled. Review change orders promptly, and if you need clarification, ask for a line-item breakdown rather than simply waiting.

Our take from the field

We work across the Valley, from newer construction in Chandler and Gilbert to older mid-century homes near Arcadia and central Scottsdale. The pattern we notice most consistently is not homeowners requesting expensive upgrades mid-project. It is condition-driven changes in homes with slab plumbing that has not been touched since the 1970s or 1980s. We recently opened a kitchen floor on a 1978 Tempe home for a simple drain reroute and found the original cast-iron drain stack had corroded through at the coupling. That was a 3,400 dollar change order that had nothing to do with the kitchen the homeowner had planned. It had to happen before we could set the new sink. The homeowner had a contingency budget and the signed change order was straightforward. The ones that go badly are the projects where that contingency does not exist and the conversation about cost happens after the floor is already open. The signed, numbered change order is not paperwork for its own sake. It is the document that keeps that conversation from becoming a dispute.

Bayside Home Builders

Planning your remodel?

Bayside gives free, itemized estimates with no pressure to sign.

Get a free estimate